120,000 m² Multi-Tower High-Rise Commercial Hub
Fabricated in Commercial & Tech Corridor. Protective coating, shop assembly. Completed 2.5 Weeks Ahead of BCA Master Plan.
Project Facts
The commercial and technical facts a contractor checks before requesting drawings.
| Location | Commercial & Tech Corridor, Singapore |
|---|---|
| Construction Type | Composite Concrete-Filled Tube (CFT) & Steel Cores |
| Project Scale | 120,000 sqm GFA; ~16,800 Tons Heavy Steel |
| Design & Execution | Vertical camber/plumbness tolerance < 1/1500 |
| Delivery Result | Completed 2.5 Weeks Ahead of BCA Master Plan |
| Industry | Multi-Tower Commercial Hub & Tech Campus |
| Our Scope | Fabrication, protective coating, shop assembly and delivery |
Project Overview
How the structure was engineered, fabricated and delivered in Commercial & Tech Corridor.
Constructing a sprawling commercial and tech complex featuring multiple interconnected mid-to-high-rise towers in land-scarce Singapore is an operational tightrope walk.
The EPC director’s primary operational fear was dual-layered: Singapore Building and Construction Authority (BCA) and Ministry of Manpower (MOM) safety standards leave zero room for uncertified welds, while extreme urban traffic constraints completely outlawed roadside component staging.
Any delay in hoisting would incur massive LTA road fines and bleed tens of thousands of dollars per shift in specialized mobile crane rentals.
Crucially, multi-level pedestrian skybridges linking the separate towers demanded that the heavy concrete-filled tube (CFT) columns and steel core trusses maintain near-zero vertical drift, or the long-span aerial bridges simply would not pin together.

Four Decisions That Made It Work
Sub-Millimeter Verticality for Flawless Br
Controlled plumbness across all core column splices within 1/1500 using continuous shop 3D laser-tracker matching, guaranteeing 42-meter aerial skybridges
100% Pre-Drilled, Zero-Hot-Work Connection
Every joint arrived pre-milled and CNC-drilled, eliminating on-site flame cutting and welding to completely bypass MOM hot-work permit bottlenecks in the c
Zero-Staging Urban JIT Logistics
Components were packed in containerized sets matching crane-hook hourly schedules, allowing direct offloading from transport flatbeds straight to high-rise
Strict BCA-Compliant Traceability
Each member shipped with complete mill test certificates (MTR), third-party ultrasonic (UT) weld records, and weatherproof QR identity tags, clearing local
The Project, As Built
Completed works, structural details and the delivery team on site.




Client Testimonial
Feedback recorded from the client after handover.
Lifting a 42-meter skybridge in downtown Singapore leaves zero margin! Shijie nailed the core alignment—pinned on the first drop!
Frequently Asked Questions
Answers engineers ask before committing to a scope like this.
What was delivered for this Singapore commercial hub?
Heavy structural steel for a multi-tower commercial and tech campus of about 120,000 sqm gross floor area on roughly 16,800 tons of steel, including composite concrete-filled tube and steel cores plus 42-metre column-free inter-tower skybridges.
Skybridges only close cleanly if the towers are built accurately. What tolerance was held?
Vertical camber and plumbness are controlled within 1/1500 across all core column splices, verified by continuous shop 3D laser-tracker matching. A 42-metre aerial bridge landing on two independently built towers leaves no allowance for accumulated error.
How do you decouple movement between two towers?
Multi-directional PTFE sliding spherical bearings at the bridge interfaces absorb differential settlement and lateral sway, so the connecting pins are not twisted as the towers move relative to each other.
There is no staging space on a city-centre plot. How were deliveries handled?
Components were packed in containerised sets matched to the tower crane’s hourly hook schedule, with a minute-by-minute loading sequence so each truck unloads directly into a lift position within about 30 minutes. Roadside storage is simply not available under LTA enforcement.
Was any site welding permitted?
None. Every joint arrives pre-milled and CNC-drilled, which bypasses MOM hot-work permit bottlenecks in the city centre, removes fire watch obligations, and eliminates weld-induced distortion on high-altitude splices.
Get Your 24-Hour BOQ and Cost Plan
See how much steel tonnage and ocean freight you can save before fabrication begins
Steel Weight Savings
1:1 Tekla 3D modeling optimizes beam-column ratios to eliminate redundant material costs.
Zero-Clash Code Verification
Checked against EN 1090 and local wind/seismic loads.
Engineer-to-Engineer Review
Verified by our lead engineers—Zero pushy sales calls, Just actionable data and factory price.