Industrial Steel Buildings · Thailand

120,000 m² Modern EV Assembly Plant

Fabricated in Rayong Automotive Industrial Hub. Protective coating, bolted trial assembly. Handed over 24 Days Ahead of Equipment Fit-out.

120,000 m²Floor Area
18,500 tSteel Tonnage
42 mSkybridge
0.35 kN/m²Solar Load

Project Facts

The commercial and technical facts a contractor checks before requesting drawings.

Project facts and specifications
IndustryEV Final Assembly & Battery Gigafactory
LocationRayong Automotive Industrial Hub, Thailand
Project Scale120,000 sqm Complex (~18,500 Tons Heavy Steel)
Design & Execution100% Pre-Drilled Bolted Connections (0% Field Welding)
Delivery ResultHanded over 24 Days Ahead of Equipment Fit-out
SkybridgeHeavy tubular truss conveyor bridges (span up to 42m)
Our ScopeFabrication, protective coating, bolted trial assembly and delivery

Project Overview

How the structure was engineered, fabricated and delivered in Rayong Automotive Industrial Hub.

Located in the Rayong industrial corridor of Thailand’s Eastern Economic Corridor (EEC), this mega manufacturing campus serves as a flagship international production hub for next-generation electric vehicles and battery modules.

For the automotive client and EPC project management, the project schedule was non-negotiable—anchored to a global vehicle launch date and rigid Start of Production (SOP) milestones.

In the EV industry, missing the SOP deadline by even two weeks triggers tens of millions of dollars in lost market momentum, dealership breach penalties, and idle labor overhead.

Dimensions, codes, inspection rates and schedule outcomes for this project are recorded in the Project Facts table above, so they can be checked before an enquiry is issued.

120,000 sqm Modern EV Assembly & Battery Gigafactory in Thailand: Long-Span Conveyor Skybridge Integration, Full-Roof Photovoltaic Loading, and Turnkey SOP Erection

Four Decisions That Made It Work

01

Sub-Millimeter Deflection Skybridge Engine

Continuous spatial tubular truss skybridges engineered via dynamic FEA, holding high-speed conveyor live deflection under $\le 1/1200$ to prevent AGV and o

02

Solar-Optimized Reverse Precambering

Long-span roof rafters were pre-cambered using precision thermal and CNC cold-bending processes, offsetting dead-loads from rooftop solar panels and HVAC l

03

Zero-Hot-Work Battery Shop Clean Assembly

High-precision multi-spindle CNC drilling guaranteed 100% bolt alignment aloft, eliminating on-site cutting torches and weld spatter near cleanroom panels

04

Crane-Synchronized 3D Container Staging

Sequenced structural members into 40HQ containers strictly by building bays, allowing crawler cranes to lift directly from the haul road without double-han

Client Testimonial

Feedback recorded from the client after handover.

Fabrication and installation team at project handover
“

Missing our EV SOP launch window meant millions in losses. Shijie eliminated all risk: the 42m conveyor skybridge bolted into place with zero deflection, overhead solar roofs drained bone-dry during monsoon storms, and 18,500 tons of steel went up with zero torch cuts. Delivering 24 days early secured our global vehicle launch.

Narongchai P.VP of Plant Construction & Engineering, Global EV Manufacturing Campus (Thailand)
120,000 m²18,500 t42 m

Frequently Asked Questions

Answers engineers ask before committing to a scope like this.

What was the structural scope of this EV gigafactory in Rayong?

About 18,500 tons of heavy steel across a 120,000 sqm campus: long-span final assembly halls, 42 m tubular truss conveyor skybridges linking the body and battery shops, and a roof structure engineered for a full rooftop PV array.

The skybridges are continuous spatial tubular trusses analysed with dynamic FEA, holding live-load deflection within L/1200. Low-friction Teflon slide bearings at each expansion tier release thermal creep and vibration, so the conveyor line stays aligned at +40°C.

Primary roof girders are reverse-precambered in the shop to offset the PV dead load of at least 0.35 kN/m2, and the envelope uses a 360-degree double-lock standing seam roof rated above 160 mm/h rainfall, with fastener spacing set for uplift.

Yes. Multi-spindle CNC drilling guaranteed bolt alignment on members erected 20 m up, so there was no site cutting torch, no grinding and no weld spatter anywhere near the battery areas. The clean-assembly requirement drove the detailing from day one.

Bays were pre-assembled on the ground and shipped in 40HQ containers sequenced strictly by building bay, so crawler cranes lifted directly from the container instead of a laydown yard. The steel package was handed over 24 days ahead of equipment fit-out.

Get Your 24-Hour BOQ and Cost Plan

See how much steel tonnage and ocean freight you can save before fabrication begins

8–15%

Steel Weight Savings

1:1 Tekla 3D modeling optimizes beam-column ratios to eliminate redundant material costs.

0.0mm

Zero-Clash Code Verification

Checked against EN 1090 and local wind/seismic loads.

100%

Engineer-to-Engineer Review

Verified by our lead engineers—Zero pushy sales calls, Just actionable data and factory price.

CE EN 1090-1•ISO 9001•ISO 14001•ISO 45001

Engineering & Inquiry Desk

Lead Engineers Online

Drawings
Drawings

🔒 100% Private and Secure, No Spam