Industrial Steel Buildings · Thailand

120,000 m² Modern EV Assembly Plant

Fabricated in Rayong Automotive Industrial Hub. Protective coating, bolted trial assembly. Handed over 24 Days Ahead of Equipment Fit-out.

120,000 m²Floor Area
18,500 tSteel Tonnage
42 mSkybridge
0,35 kN/m²Solar Load

Datos del proyecto

Los aspectos comerciales y técnicos que un contratista comprueba antes de solicitar los planos.

Datos y especificaciones del proyecto
SectorEV Final Assembly & Battery Gigafactory
UbicaciónRayong Automotive Industrial Hub, Thailand
Project Scale120,000 sqm Complex (~18,500 Tons Heavy Steel)
Diseño y ejecución100% Pre-Drilled Bolted Connections (0% Field Welding)
Delivery ResultHanded over 24 Days Ahead of Equipment Fit-out
SkybridgeHeavy tubular truss conveyor bridges (span up to 42m)
Nuestro ámbito de actuaciónFabrication, protective coating, bolted trial assembly and delivery

Descripción del proyecto

Compartir

How the structure was engineered, fabricated and delivered in Rayong Automotive Industrial Hub.

Located in the Rayong industrial corridor of Thailand’s Eastern Economic Corridor (EEC), this mega manufacturing campus serves as a flagship international production hub for next-generation electric vehicles and battery modules.

For the automotive client and EPC project management, the project schedule was non-negotiable—anchored to a global vehicle launch date and rigid Start of Production (SOP) milestones.

In the EV industry, missing the SOP deadline by even two weeks triggers tens of millions of dollars in lost market momentum, dealership breach penalties, and idle labor overhead.

Dimensions, codes, inspection rates and schedule outcomes for this project are recorded in the Project Facts table above, so they can be checked before an enquiry is issued.

Gigafábrica moderna de 120 000 m² dedicada al montaje de vehículos eléctricos y baterías en Tailandia: integración de pasarelas elevadas con cintas transportadoras de gran luz, instalación fotovoltaica en toda la cubierta y montaje «llave en mano» para el inicio de la producción

Cuatro decisiones clave

01

Sub-Millimeter Deflection Skybridge Engine

Continuous spatial tubular truss skybridges engineered via dynamic FEA, holding high-speed conveyor live deflection under $\le 1/1200$ to prevent AGV and o

02

Solar-Optimized Reverse Precambering

Long-span roof rafters were pre-cambered using precision thermal and CNC cold-bending processes, offsetting dead-loads from rooftop solar panels and HVAC l

03

Zero-Hot-Work Battery Shop Clean Assembly

High-precision multi-spindle CNC drilling guaranteed 100% bolt alignment aloft, eliminating on-site cutting torches and weld spatter near cleanroom panels

04

Crane-Synchronized 3D Container Staging

Sequenced structural members into 40HQ containers strictly by building bays, allowing crawler cranes to lift directly from the haul road without double-han

Testimonio del cliente

Comentarios del cliente recogidos tras la entrega.

Equipo de fabricación e instalación en el momento de la entrega del proyecto
“

Missing our EV SOP launch window meant millions in losses. Shijie eliminated all risk: the 42m conveyor skybridge bolted into place with zero deflection, overhead solar roofs drained bone-dry during monsoon storms, and 18,500 tons of steel went up with zero torch cuts. Delivering 24 days early secured our global vehicle launch.

Narongchai P.Vicepresidente de Construcción e Ingeniería de Plantas, Campus Global de Fabricación de Vehículos Eléctricos (Tailandia)
120,000 m²18,500 t42 m

Preguntas frecuentes

Preguntas que se plantean los ingenieros antes de comprometerse con un proyecto de este alcance.

What was the structural scope of this EV gigafactory in Rayong?

About 18,500 tons of heavy steel across a 120,000 sqm campus: long-span final assembly halls, 42 m tubular truss conveyor skybridges linking the body and battery shops, and a roof structure engineered for a full rooftop PV array.

The skybridges are continuous spatial tubular trusses analysed with dynamic FEA, holding live-load deflection within L/1200. Low-friction Teflon slide bearings at each expansion tier release thermal creep and vibration, so the conveyor line stays aligned at +40°C.

Primary roof girders are reverse-precambered in the shop to offset the PV dead load of at least 0.35 kN/m2, and the envelope uses a 360-degree double-lock standing seam roof rated above 160 mm/h rainfall, with fastener spacing set for uplift.

Yes. Multi-spindle CNC drilling guaranteed bolt alignment on members erected 20 m up, so there was no site cutting torch, no grinding and no weld spatter anywhere near the battery areas. The clean-assembly requirement drove the detailing from day one.

Bays were pre-assembled on the ground and shipped in 40HQ containers sequenced strictly by building bay, so crawler cranes lifted directly from the container instead of a laydown yard. The steel package was handed over 24 days ahead of equipment fit-out.

Obtén tu presupuesto y plan de costos en 24 horas

Descubre cuánto puedes ahorrar en tonelaje de acero y en flete marítimo antes de que comience la fabricación

8–15%

Reducción del peso del acero

El modelado 3D 1:1 de Tekla optimiza las relaciones viga-columna para eliminar los costos de material redundante.

0,0 mm

Verificación de código sin conflictos

Se ha verificado de acuerdo con la norma EN 1090 y las cargas eólicas y sísmicas locales.

100%

Revisión de ingeniero a ingeniero

Verificado por nuestros ingenieros principales: sin llamadas de ventas agresivas, solo datos útiles y precio de fábrica.

CE EN 1090-1•ISO 9001•ISO 14001•ISO 45001

Mostrador de Ingeniería e Investigación

Ingenieros principales en línea

Dibujos
Dibujos

🔒 100 % privado y seguro, sin spam