Commercial Steel Buildings · Cambodia

2,560 m² Flex Space Buildings, Cambodia

Three connected single-slope buildings with sixteen framed openings let office, workshop and storage tenants share one shell in Cambodia.

2,560 m²Under roof
3 blocksConnected buildings
88 tStructural steel
10 weeksOn site

Project Facts

Facts a contractor checks first: Flexible commercial and light industrial space - Three connected single-slope steel frames with repeated unit bays and graphite base course, 2,560 m² under roof across three connected buildings.

Project facts and specifications
IndustryFlexible commercial and light industrial space - offices, workshops, service counters and storage under one roof
Construction typeThree connected single-slope steel frames with repeated unit bays and graphite base course - cool grey-white cladding, graphite window and door frames
Project scale2,560 m² under roof across three connected buildings - 88 t of fabricated structural steel
LocationTown-edge commercial site, Cambodia - hot humid tropical climate, monsoon rain, bright hazy sky
CollaboratorsLocal civil works · glazing and fit-out suppliers - frame set around the unit grid and the shared parking court
Delivery10 weeks on site - envelope closed before tenant fit-out
Our scopeStructural design and 3D modelling · three single-slope primary steel frames · secondary steel and floor bracing · silver-grey roof sheeting with gutters · cool grey-white wall cladding · graphite base course, window and door frames · repeated unit entrance openings · high-level square windows · canopies · downpipes · erection drawings and site support

Project Overview

A flex building works when every unit gets the same shell and its own front door.

SynJect supplied 88 tonnes of structural steel for three connected flex space buildings totalling 2,560 m² in Cambodia, stepped along one shared court. Offices, light workshops and storage tenants each get a separate framed entrance off that court without changing the frame.

The frame follows one repeated grid. Column centres, rafter bracing, cladding panels and graphite window frames stay identical along the whole elevation, while a dark base course and high-level square windows give the cool grey-white cladding a consistent street frontage. Canopies mark each unit entry.

The humid tropical site drives the detailing: shallow roof falls and continuous eave gutters shed monsoon rain clear of every unit entrance, sealed cladding with gasketed trims keeps driven rain out, and galvanized steel protects each lintel, canopy and downpipe.

Completed 2,560 m² flex space buildings in Cambodia with cool grey-white cladding, graphite base course and an empty parking court

Four Decisions That Made It Work

01

Repeated Bay Grid

One bay module keeps frames and panels standard across all three blocks.

02

Separate Entrances

Each tenant gets a door off the shared court.

03

Three-Block Frontage

Each block keeps its own roof line and street frontage.

04

Monsoon-Ready Roof

Sized gutters shed intense seasonal rain.

Client Testimonial

Feedback from Commercial Asset Manager after handover.

SynJect erection crew in hard hats holding a red company banner on the parking court of the completed flex space buildings in Cambodia
Fabrication and installation team on site
“

One repeated bay module meant one set of shop drawings. Tenants fitted out in any order and the frame never changed.

Commercial Asset ManagerFlex space property operator, Cambodia
2,560 m² under roofThree connected blocksShared parking court

Frequently Asked Questions

Common questions from buyers specifying this building type.

How is a 2,560 m² flex space project in Cambodia quoted?

A 2,560 m² flex space project in Cambodia is quoted against an itemised bill of quantities rather than a flat rate per square metre, because unit count, floor count, column grid, floor loading, glazing extent, monsoon wind and rainfall loads, coating specification and delivery distance all change the steel tonnage that SynJect has to fabricate and ship. The BOQ separates primary frames, rafter bracing and purlins, secondary steel, roof and wall sheeting, entrance openings, canopies, trims, fasteners and coatings so each line can be compared between bidders. Send SynJect the unit schedule, floor count and site location and the quantities come back itemised against those inputs.

The steel package for the 2,560 m² project in Cambodia covers structural design and 3D modelling, the three single-slope primary frames, rafter bracing and purlins, secondary steel, silver-grey roof sheeting with gutters, cool grey-white cladding, the graphite base course, window and door frames, sixteen framed openings and the entry canopies as one coordinated supply. Earthworks, foundations, floor slabs, glazing, tenant fit-out, partitions, HVAC, parking paving and utilities sat outside that package on this project. The table below shows the boundary as it was applied on the delivered project. In the steel package Outside the package Primary frames, rafter bracing and purlins Earthworks, foundations and floor slabs Roof sheeting, wall cladding, gutters and trims Glazing, partitions and tenant fit-out Unit entrance openings, windows and canopies HVAC, parking paving and utilities 3D model, shop drawings and erection drawings Local erection labour, cranes and permits

A steel flex building in Cambodia is designed to the local authority load requirements together with recognised steel design standards for the frames, connections and coatings. For the delivered 2,560 m² project, the design basis recorded roof imposed loading, monsoon wind and rainfall exposure, glazed entrance lintel loads and the humidity assumptions used for the coating specification. Every SynJect project is modelled in 3D before fabrication, so connection schedules and code checks stay traceable from model to shop drawing. Ask for the design basis report with the BOQ and the assumptions are visible before cutting starts.

Fabrication, shipping and erection for a Cambodia flex building run as one coordinated sequence: SynJect fabricates and trial-assembles the repeated frames at the works, ships members in erection order, and hands the site team a crane study plus marked erection drawings before the first lift. On this project, the whole envelope was closed before tenant fit-out began, so partitions and services were installed onto dry floors. The sequencing plan, crane study and erection drawings are part of the SynJect package, so local contractors price lifts against drawings.

A repeated bay module suits flex space buildings because each tenant gets a defined lease area with its own glazed entrance, while one column grid keeps frame details, cladding panels and window sizes identical across the whole elevation. That makes leasing, metering and fit-out predictable from the first tenant to the last. The shared parking court sits outside the column line, so vehicle movement never conflicts with the unit entrances. One large shell would need demising walls later and would give tenants no identifiable frontage.

Monsoon rain and tropical humidity in the delivered Cambodia buildings are handled at roof and wall level: shallow roof falls drive intense rain into continuous eave gutters, downpipes drop clear of every unit entrance, entry canopies shield the glazed doors, and sealed cool grey-white cladding with gasketed trims keeps humid air out. High-level square windows admit daylight without putting large glazed areas at the windward corners. Internal humidity control belongs to the HVAC package, but the sealed envelope keeps that system sized to a predictable load.

Glazing and tenant fit-out at a flex building sit outside the SynJect steel package and are delivered by the local glazing and fit-out contractors against our frame and hold-down details. On the Cambodia building, glazing heights, canopy levels, slab levels and partition lines were agreed between the packages before the units were specified. Each tenant sets its own internal layout, not the frame, so the demising and services interfaces have to be signed off early. Request the interface drawing set with the BOQ and the steel-to-slab boundary becomes unambiguous.

The 2,560 m² figure covers everything under roof on the delivered project in Cambodia: all three connected buildings, the covered entry zones and the enclosed service passages inside the building line. The open parking court, drive aisles, site drainage and perimeter fencing are excluded from that number. All three blocks are counted, so bids stay comparable between suppliers. Ask any bidder to state the split between the three blocks before comparing offers.

The graphite base course on these Cambodia buildings gives the long cool grey-white elevation a durable lower band where parking courts, trolleys and deliveries cause the most wear, and it visually anchors the repeated unit entrances. It is a cladding and trim choice, not a change to the primary frame or the column grid. Because it follows the unit grid, the band can be renewed later without touching the structure. The same graphite finish is used on every window and door frame for a consistent frontage.

More units can be added at the end of the building line, because the end frame was detailed as a removable future-extension frame, not a permanent braced wall. Floor beams, cladding, window sizes and purlin centres all run to the same grid, so another unit continues the envelope with no step in the roof line. SynJect recorded the extension assumptions in the design basis, including the extra unit load and the future downpipe position. Confirm the extension unit in the first BOQ and the end-frame connections are fabricated ready for it.

Get Your 24-Hour BOQ and Cost Plan

See how much steel tonnage and ocean freight you can save before fabrication begins

8–15%

Steel Weight Savings

1:1 Tekla 3D modeling optimizes beam-column ratios to eliminate redundant material costs.

0.0mm

Zero-Clash Code Verification

Checked against EN 1090 and local wind/seismic loads.

100%

Engineer-to-Engineer Review

Verified by our lead engineers—Zero pushy sales calls, Just actionable data and factory price.

CE EN 1090-1•ISO 9001•ISO 14001•ISO 45001

Engineering & Inquiry Desk

Lead Engineers Online

Drawings
Drawings

🔒 100% Private and Secure, No Spam