Home / Solutions / Solar Power Solutions / Ground-Mounted Solar Power Solution
Ground-Mounted Solar Power Solution
Ground mount looks simple until the first pile goes in. These four issues decide whether the array is still standing square after the first storm season.
Challenges & Solutions
Ground mount looks simple until the first pile goes in. These four issues decide whether the array is still standing square after the first storm season.
Soil conditions are unknown until the first pile goes in, and the quotation was usually built before anyone tested it.
We work from geotechnical data and confirm it on site by recording installation torque on every pile, backed by a load test on a sample at the start of works. Soft spots show up in the record instead of in the first storm.
The array is light. The design case is extraction, not bearing, and a pile sized for downward load will fail the case that matters.
Pull-out resistance governs the pile design, checked to ASCE 7 or EN 1991-1-4 with the site exposure and array height. Corners and the windward edge get deeper piles or closer spacing.
A sloping site with poor drainage reshapes the array, and the layout drawn on a flat survey does not survive contact with the ground.
Post lengths are varied to follow the slope rather than cutting and filling it, and the drainage path is kept clear of the rows. The layout is set from a topographical survey, not a satellite image.
The buried section cannot be repainted, and the corrosion allowance is where cheap piles quietly fail.
Buried lengths get a heavier galvanizing — typically 80 μm or more — and cut ends and welds are repaired with zinc-rich compound before installation. Above-ground coating follows the site category.
Technical Specifications
Values below are what we fabricate routinely. Final embedment and section are confirmed against the geotechnical report and the governing wind case.
| Parameter | Specification |
|---|---|
| Application | Ground-mounted commercial and utility arrays |
| Tilt Angle | 0–35° fixed, set by latitude and season |
| Post Section | C-section, H-section or CHS, hot-dip galvanized |
| Foundation | Helical ground screw, driven pile or concrete pier |
| Embedment | 1.0–2.5 m typical — set by geotechnical data and frost depth |
| Wind Design | ASCE 7 / EN 1991-1-4, pull-out governing |
| Corrosion Protection | Buried ≥ 80 μm galvanizing; above ground per ISO 12944 |
| Row Spacing | Set to avoid inter-row shading at the critical sun angle |
| Execution Standard | EN 1090-2, EN 1997-1, ISO 12944 |
| Erection | Bolted, no site welding |
NoteStructural calculations shall be verified against site wind, snow and seismic data before fabrication.
How Your Project Is Built
The structure is the cheap part. The sequence below exists to get the foundation and the wind case right before any steel is cut.
Geotechnical Review & Layout
Soil report, topography and drainage are reviewed before any structure is priced. The array layout follows the ground, the access roads and the cable routes together.
- Geotechnical data reviewed, or a test pile programme agreed
- Topographical survey used for post lengths and row spacing
- Drainage path and access routes kept clear of the array
Structure, Foundation & Wind Case
Post section, embedment and rail span are calculated together against the governing wind case, with the corner and edge zones treated separately from the field.
- Pull-out and bearing capacity checked for the actual soil profile
- Wind uplift calculated with site exposure and array height
- Rail and purlin sections matched to post spacing and snow load
Supply, Pile Support & Handover
Piles and structure are packed by row for sequential installation. Installation torque records and the load test report form part of the handover.
- Packing by row and array, labelled for sequential erection
- Installation torque recorded per pile and issued as a report
- As-built layout, coating specification and test records handed over
Qualification Certificate
Your projects are protected by world-class standards. From CE (EN 1090) to ISO 9001, our qualifications are not just paper—they are the rigorous daily reality on our shop floor.




Recommended Product Systems
Ground mount structures, piles, rails and ballast, engineered against the soil and wind case of the specific site.
SynJect engineers heavy-duty solar mounting structures and tracker supports designed for utility-scale solar farms. Engineered to withstand extreme wind uplift and heavy snow loads, our modular steel frameworks guarantee rapid, bolt-together field assembly on any terrain.
Related Projects
Frequently Asked Questions
How deep do the piles need to go?
Below the frost line and deep enough to develop the required pull-out resistance — typically 1.0–2.5 m. It is a geotechnical answer, not a standard detail, which is why we ask for soil data before pricing.
What if the soil report is not available?
We agree a test pile programme at the start of works: install a few piles, load test one, and record torque across the site. The results set the embedment for the rest. It is cheaper than over-driving every pile or discovering a soft patch later.
Ground screw or concrete foundation?
Ground screws for most soils and much faster installation. Concrete piers where the soil will not hold a screw, or where the specification requires them. Rock needs a drilled and grouted pin, which is a different mobilisation.
How is row spacing decided?
By the shadow length at the lowest sun angle of the critical season, plus a margin. Closer rows save land but shade; wider rows cost land and cable. The optimum depends on land price and latitude.
What wind speed is the structure designed for?
Calculated per project to ASCE 7 or EN 1991-1-4 using the site basic wind speed, terrain category and array height. A generic rating without those assumptions is not a design.
Does the array need drainage?
The site does. Rows should not block the natural fall, and post installation should not create ponding points. On flat sites this is often the difference between a stable array and one that settles differentially.
How is the structure protected against corrosion?
Buried sections get a heavier galvanizing, typically 80 μm or more, because they cannot be repainted. Above-ground coating follows the site category to ISO 12944, and cut ends are repaired with zinc-rich compound.
Can the array be extended later?
Yes, if the rows are laid out on a module that allows it and the foundation design leaves spare capacity. Retrofitting rows into an existing layout usually compromises the shading study and the cable routing.
Get Your 24-Hour BOQ and Cost Plan
See how much steel tonnage and ocean freight you can save before fabrication begins
Steel Weight Savings
1:1 Tekla 3D modeling optimizes beam-column ratios to eliminate redundant material costs.
Zero-Clash Code Verification
Checked against EN 1090 and local wind/seismic loads.
Engineer-to-Engineer Review
Verified by our lead engineers—Zero pushy sales calls, Just actionable data and factory price.
CE EN 1090-1•ISO 9001•ISO 14001•ISO 45001
Lead Engineers Online
🔒 100% Private and Secure, No Spam